How many days in advance must the DHEC be notified about transfers?

  1. 7 days

  2. 14 days

  3. 30 days

  4. 1 day

The correct answer is: 14 days

The requirement to notify the Department of Health and Environmental Control (DHEC) 14 days in advance regarding transfers is based on regulatory provisions designed to ensure that proper procedures are followed for the safe and effective management of pharmacy operations. This timeline allows adequate time for the DHEC to review the proposed changes, assess any potential impacts on public health or safety, and ensure compliance with applicable laws and regulations. Notifying the DHEC well in advance helps to facilitate a smooth transition, allowing all necessary documentation and oversight to be completed without rushing. It ensures that all stakeholders are adequately informed and that any potential concerns can be addressed proactively. In contrast, shorter notice periods may not afford sufficient time for due diligence, regulatory review, and the resolution of any issues that may arise prior to the transfer, which could jeopardize compliance and patient safety. Therefore, the requirement for a 14-day notification period is a necessary regulatory measure in this context.